Chinese Journal of Management Science ›› 2022, Vol. 30 ›› Issue (4): 132-143.doi: 10.16381/j.cnki.issn1003-207x.2020.0712

• Articles • Previous Articles     Next Articles

Construction Period-Cost Optimization of Program Based on Critical Chain Method under Multi-Resource Constraints

FENG Jing-chun1,2,3, DONG Ling-li1   

  1. 1. Institute of Project Management, Business School, Hohai University, Nanjing 211100, China;2. International River Research Centre, Hohai University, Nanjing 211100, China;3. Jiangsu Provincial Collaborative Innovation Center of World Water Valley and Water Ecological Civilization, Nanjing211100, China
  • Received:2020-04-21 Revised:2020-12-29 Online:2022-04-20 Published:2022-04-26
  • Contact: 丰景春 E-mail:feng.jingchun@163.com

Abstract: In practice, large-scale projects are in the environment of multi-stakeholder, multi-resource demand, multi-stage, and multi-contract projects. Since the theory and method of single project management do not consider the impact of contracted project construction period compression on construction period and cost of subsequent contracted projects, the partial network generated by the logical relationship of the project, and program under limited resources, they cannot satisfy the demand of construction period-cost optimization of large-scale projects.It can be seen that considering the impact of the logical relationship between the contracted projects in the program on the compression cost is more in line with the engineering reality and of more practical significance. Therefore, it is particularly important to study the construction period-cost optimization of program under multi-resource constraints.

Key words: program;sub-network;contracted project;construction period-cost optimization;critical chain;multi-resource constrains