%A FENG Jing-chun, DONG Ling-li %T Construction Period-Cost Optimization of Program Based on Critical Chain Method under Multi-Resource Constraints %0 Journal Article %D 2022 %J Chinese Journal of Management Science %R 10.16381/j.cnki.issn1003-207x.2020.0712 %P 132-143 %V 30 %N 4 %U {http://www.zgglkx.com/CN/abstract/article_17852.shtml} %8 2022-04-20 %X In practice, large-scale projects are in the environment of multi-stakeholder, multi-resource demand, multi-stage, and multi-contract projects. Since the theory and method of single project management do not consider the impact of contracted project construction period compression on construction period and cost of subsequent contracted projects, the partial network generated by the logical relationship of the project, and program under limited resources, they cannot satisfy the demand of construction period-cost optimization of large-scale projects.It can be seen that considering the impact of the logical relationship between the contracted projects in the program on the compression cost is more in line with the engineering reality and of more practical significance. Therefore, it is particularly important to study the construction period-cost optimization of program under multi-resource constraints.