Chinese Journal of Management Science ›› 2026, Vol. 34 ›› Issue (2): 144-155.doi: 10.16381/j.cnki.issn1003-207x.2024.1589
Previous Articles Next Articles
Yukang He1, Tao Jia2,3, Weibo Zheng2,3(
)
Received:2024-09-13
Revised:2024-12-23
Online:2026-02-25
Published:2026-02-04
Contact:
Weibo Zheng
E-mail:zhengweb@mail.xjtu.edu.cn
CLC Number:
Yukang He,Tao Jia,Weibo Zheng. Decentralized Resource Allocation Based Multi-project Scheduling Optimization to Dynamically Balance Cash Flows[J]. Chinese Journal of Management Science, 2026, 34(2): 144-155.
"
| 参数 | 设置 | 参数 | 设置 |
|---|---|---|---|
| 项目数 | 3 | 全局资源强度 | 0.5,0.75,1 |
| 项目非虚活动数 | 10,20,40,60 | 全局资源因子 | 0.5,0.75,1 |
| 项目的开始和结束活动数 | 从2、3、4中按等概率随机选取 | 活动工期 | 从 |
| 项目的最大紧前紧后活动数 | 4 | 活动成本 | 从 |
| 局部资源种类数 | 4 | 项目预付款比例 | 0.05,0.1,0.15 |
| 局部资源因子 | 0.5,0.75,1 | 项目支付比例 | 0.8,0.85,0.9 |
| 局部资源强度 | 0.5,0.75,1 | 项目开始时间 | 从 |
| 全局资源种类数 | 2 | 单位时期折现率 | 0.006,0.008,0.01 |
| 活动挣值 | 项目里程碑活动 | 里程碑活动数 | |
| 活动对局部资源的需求量 | 从 | 项目截止时间 | |
| 活动对全局资源的需求量 | 从 |
"
| 参数 | 取值 | SA-TS-IM | SA-TS | SA | TS | MSII | |||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 10 | 5,334 | 1.66 | 2.81 | 3,063 | 5.10 | 9.65 | 2,979 | 6.44 | 9.92 | 3,561 | 6.26 | 12.09 | 1,854 | 13.37 | 26.20 | 3.44 | 4.78 | 4.60 | |
| 20 | 5,766 | 1.27 | 2.86 | 3,519 | 5.69 | 8.87 | 3,288 | 7.58 | 12.20 | 3,111 | 7.35 | 12.14 | 1,089 | 22.56 | 32.20 | 4.42 | 6.31 | 6.08 | |
| 40 | 6,174 | 1.15 | 2.34 | 3,900 | 6.72 | 10.73 | 3,207 | 8.36 | 14.26 | 2,697 | 9.26 | 17.64 | 258 | 37.18 | 52.07 | 5.57 | 7.21 | 8.11 | |
| 60 | 6,495 | 0.53 | 1.00 | 3,429 | 7.84 | 13.22 | 3,369 | 9.70 | 18.55 | 2,763 | 10.07 | 17.73 | 0 | 46.60 | 69.88 | 7.31 | 9.17 | 9.54 | |
| 0.5 | 8,331 | 0.92 | 2.01 | 4,914 | 7.16 | 13.17 | 4,566 | 9.12 | 18.55 | 3,903 | 9.59 | 17.73 | 810 | 32.67 | 65.07 | 6.24 | 8.20 | 8.67 | |
| 0.75 | 7,995 | 1.16 | 2.27 | 4,722 | 6.75 | 13.22 | 4,182 | 8.26 | 13.50 | 3,933 | 7.85 | 12.59 | 1,137 | 29.60 | 69.88 | 5.59 | 7.10 | 6.69 | |
| 1 | 7,443 | 1.38 | 2.86 | 4,275 | 5.12 | 9.61 | 4,095 | 6.68 | 10.05 | 4,296 | 7.28 | 15.10 | 1,254 | 27.54 | 53.14 | 3.74 | 5.30 | 5.90 | |
| 0.5 | 7,266 | 1.41 | 2.86 | 4,143 | 5.09 | 10.32 | 3,993 | 6.31 | 9.52 | 4,362 | 5.64 | 9.87 | 1,437 | 26.76 | 45.40 | 3.68 | 4.90 | 4.23 | |
| 0.75 | 8,055 | 1.22 | 2.26 | 4,755 | 6.55 | 13.22 | 4,215 | 8.38 | 15.18 | 3,978 | 8.54 | 15,72 | 1,113 | 28.78 | 56.95 | 5.33 | 7.16 | 7.32 | |
| 1 | 8,448 | 0.80 | 1.60 | 5,013 | 7.38 | 12.74 | 4,635 | 9.36 | 18.55 | 3,792 | 10.55 | 17.73 | 651 | 34.25 | 69.88 | 6.58 | 8.56 | 9.75 | |
| 1.2 | 7,383 | 1.33 | 2.86 | 4,278 | 5.64 | 11.13 | 4,080 | 6.80 | 12.58 | 4,419 | 6.33 | 11.66 | 1,368 | 25.74 | 48.14 | 4.31 | 5.47 | 5.00 | |
| 1.4 | 7,995 | 1.18 | 2.34 | 4,557 | 6.16 | 11.59 | 4,248 | 8.22 | 14.38 | 4,134 | 8.45 | 16.82 | 1,044 | 28.80 | 69.88 | 4.98 | 7.04 | 7.27 | |
| 1.6 | 8,391 | 0.95 | 1.92 | 5,076 | 7.25 | 13.22 | 4,515 | 9.08 | 18.55 | 3,579 | 9.96 | 17.73 | 789 | 35.25 | 66.03 | 6.30 | 8.13 | 9.01 | |
| 全部算例 | 23,769 | 1.15 | 2.86 | 13,911 | 6.35 | 13.22 | 12,843 | 8.03 | 18.55 | 12,132 | 8.25 | 17.73 | 3,201 | 29.93 | 69.88 | 5.20 | 6.88 | 7.10 | |
| [1] | Payne J H. Management of multiple simultaneous projects: A state-of-the-art review[J]. International Journal of Project Management,1995, 13(3): 163-168. |
| [2] | 李飞飞, 徐哲, 刘东宁, 等. 分布式资源受限多项目调度问题研究综述[J]. 工业工程与管理, 2023, 28(5): 199-210. |
| Li F F, Xu Z, Liu D N, et al. A literature review of distributed resource-constrained multi-project scheduling problem[J]. Industrial Engineering and Management, 2023, 28(5): 199-210. | |
| [3] | Russell A H. Cash flows in networks[J]. Management Science, 1970, 16(5): 357-373. |
| [4] | Smith-Daniels D E, Padman R, Smith-Daniels V L. Heuristic scheduling of capital constrained projects[J]. Journal of Operations Management, 1996,14(3): 241-254. |
| [5] | 何正文, 刘人境, 胡信布. 基于合同双方交互作用的项目调度优化[J]. 管理科学学报, 2014, 17(8): 48-59. |
| He Z W, Liu R J, Hu X B. Project scheduling optimization based on interaction between two parties of contracts[J]. Journal of Management Sciences in China, 2014, 17(8): 48-59. | |
| [6] | Leyman P, Vanhoucke M. Capital- and resource-constrained project scheduling with net present value optimization[J]. European Journal of Operational Research, 2017, 256(3): 757-776. |
| [7] | 梁洋洋, 王田, 崔南方. 基于资源流网络优化的Max-npv项目调度[J].中国管理科学,2022,30(7): 241-251. |
| Liang Y Y, Wang T, Cui N F. Max—NPV project scheduling based on optimizing the resource flow network[J]. Chinese Journal of Management Science, 2022, 30(7): 241-251. | |
| [8] | 何一丹, 何正文, 王能民, 等. 共享经济环境下的资源约束Max-NPV多项目调度优化[J]. 中国管理科学, 2024, 32(9): 260-270. |
| He Y D, He Z W, Wang N M, et al. Resource-constrained max-NPV multi-project scheduling optimization under sharing economy environment[J]. Chinese Journal of Management Science,2024,32(9): 260-270. | |
| [9] | Rostami S, Creemers S, Leus R. Maximizing the net present value of a project under uncertainty: Activity delays and dynamic policies[J]. European Journal of Operational Research, 2024, 317(1): 16-24. |
| [10] | Yazdani M, Aouam T, Vanhoucke M. An exact decomposition technique for the deadline-constrained discrete time/cost trade-off problem with discounted cash flows[J]. Computers & Operations Research, 2024, 163: 106491. |
| [11] | 何 华, 曹芳芳, 何正文,等. 双重资源约束下的净现值最大化多项目调度优化[J]. 中国管理科学, 2025,33(12):146-159. |
| He H, Cao FF, He ZW, et al. Max-NPV multi-project scheduling optimization under dual resource constraints[J]. Chinese Journal of Management Science, 2025,33(12):146-159. | |
| [12] | Confessore G, Giordani S, Rismondo S. A market-based multi-agent system model for decentralized multi-project scheduling[J]. Annals of Operations Research, 2007, 150(1): 115-135. |
| [13] | Wauters T, Verbeeck K, De Causmaecker P, et al. A learning-based optimization approach to multi-project scheduling[J]. Journal of Scheduling, 2015, 18(1): 61-74. |
| [14] | 彭武良, 陈良威, 马雪丽. 分散式项目群调度的双目标优化方法研究[J]. 管理工程学报, 2021, 35(5): 131-140. |
| Peng W L, Chen L W, Ma X L. Research on the double-objective optimization for decentralized project group scheduling[J]. Journal of Industrial Engineering and Engineering Management,2021, 35(5): 131-140. | |
| [15] | 刘婉君, 张静文, 刘万琳. 基于拍卖机制的资源转移时间型动态分布式多项目调度[J]. 中国管理科学, 2022, 30(8): 117-129. |
| Liu W J, Zhang J W, Liu W L. Dynamic decentralized resource-constrained multi-project scheduling problem with transfer times based on auction mechanism[J]. Chinese Journal of Management Science, 2022, 30(8): 117-129. | |
| [16] | 胡雪君, 赵雁, 单汩源, 等. 基于自适应大邻域搜索的鲁棒多项目调度方法[J]. 中国管理科学, 2022, 30(9): 217-231. |
| Hu X J, Zhao Y, Shan G Y, et al. An adaptive large neighborhood search metaheuristic for robust multi-project scheduling[J]. Chinese Journal of Management Science, 2022, 30(9): 217-231. | |
| [17] | He Y, Jia T, Zheng W. Tabu search for dedicated resource-constrained multiproject scheduling to minimise the maximal cash flow gap under uncertainty[J]. European Journal of Operational Research, 2023, 310(1): 34-52. |
| [18] | 有维宝, 徐哲, 刘东宁. 基于拍卖谈判机制的分布式多技能多项目调度[J]. 运筹与管理, 2024, 33(1): 1-8. |
| You W B, Xu Z, Liu D N. An auction-based negotiation mechanism to distributed multi-skilled multi-project scheduling problem[J]. Operations Research and Management Science, 2024, 33(1): 1-8. | |
| [19] | Satic U, Jacko P, Kirkbride C. A simulation-based approximate dynamic programming approach to dynamic and stochastic resource-constrained multi-project scheduling problem[J]. European Journal of Operational Research, 2024, 315(2): 454-469. |
| [20] | He Y, Jia T, Zheng W. Simulated annealing for centralised resource-constrained multiproject scheduling to minimise the maximal cash flow gap under different payment patterns[J]. Annals of Operations Research, 2024, 338(1): 115-149. |
| [21] | Brucker P, Drexl A, Möhring R, et al. Resource-constrained project scheduling: Notation, classification, models, and methods[J]. European Journal of Operational Research, 1999, 112(1): 3-41. |
| [22] | Hartmann S, Briskorn D. An updated survey of variants and extensions of the resource-constrained project scheduling problem[J]. European Journal of Operational Research, 2022, 297(1): 1-14. |
| [23] | Gómez Sánchez M, Lalla-Ruiz E, Fernández Gil A, et al. Resource-constrained multi-project scheduling problem: A survey[J]. European Journal of Operational Research, 2023, 309(3): 958-976. |
| [24] | 李飞飞, 徐哲, 于静. 基于序贯博弈谈判机制的分布式多项目调度[J]. 系统工程理论与实践, 2018(3): 696-709. |
| Li F F, Xu Z, Yu J. A sequential game-based negotiation approach to distributed multi-project scheduling problem[J]. Systems Engineering-Theory & Practice, 2018(3): 696-709. | |
| [25] | Blazewicz J, Lenstra J K, Kan A H G R. Scheduling subject to resource constraints: Classification and complexity[J]. Discrete Applied Mathematics, 1983, 5(1): 11-24. |
| [26] | Pellerin R, Perrier N, Berthaut F. A survey of hybrid metaheuristics for the resource-constrained project scheduling problem[J]. European Journal of Operational Research, 2020, 280(2): 395-416. |
| [27] | Kolisch R, Sprecher A. PSPLIB - A project scheduling problem library[J]. European Journal of Operational Research, 1997, 96(1): 205-216. |
| [28] | Browning T R, Yassine A A. A random generator of resource-constrained multi-project network problems[J]. Journal of Scheduling, 2010, 13(2): 143-161. |
| [29] | Browning T R, Yassine A A. Resource-constrained multi-project scheduling: Priority rule performance revisited[J]. International Journal of Production Economics, 2010, 126(2): 212-228. |
| [1] | Baofeng Tian, Jingwen Zhang, Lubo Li, Junjie Chen. Integrated Resource-constrained Project Scheduling and Material Ordering Problem with Limited Storage Space [J]. Chinese Journal of Management Science, 2025, 33(8): 144-155. |
| [2] | Xiao Cui, Zhengwen He, Nengmin Wang. Optimization of Reactive Project Scheduling with Stochastic Resource Requirements Considering Information Handling Input [J]. Chinese Journal of Management Science, 2025, 33(8): 218-229. |
| [3] | Yanting Wang, Weibo Zheng, Zhiqiang Ma, Zhengwen He. Robustness Threshold-based Max-NPV Project Scheduling Optimization on Different Clients’ Payment Modes [J]. Chinese Journal of Management Science, 2025, 33(4): 185-196. |
| [4] | Hua He, Zhengwen He, Fangfang Cao, Nengmin Wang. Max-NPV Multi-project Scheduling Optimization under Dual Resource Constraints [J]. Chinese Journal of Management Science, 2025, 33(12): 146-159. |
| [5] | Lei Zhu, Yaofeng Cui, Jiarui Wang, Jiahao Wu. Dynamic Optimization Model for Renewable Resource Development: An Example of Onshore Wind [J]. Chinese Journal of Management Science, 2025, 33(11): 336-344. |
| [6] | Yidan He,Zhengwen He,Nengmin Wang,Zhiqiang Ma. Resource-constrained Max-NPV Multi-project Scheduling Optimization under Sharing Economy Environment [J]. Chinese Journal of Management Science, 2024, 32(9): 260-270. |
| [7] | Zheng Wang,Peng Lu,Xiangpei Hu. Method of Locating Racks in Mobile-Rack Warehousing System [J]. Chinese Journal of Management Science, 2024, 32(8): 84-94. |
| [8] | Jingchun Feng,Yaqi Yan,Ke Zhang,Daisong Hu. Robust Optimization Model of Water Environment Treatment Portfolio of Big Rivers for Maximizing Enterprise Income——Taking Yangtze River Protection as an Example [J]. Chinese Journal of Management Science, 2024, 32(6): 323-334. |
| [9] | Song ZHAO, Zhe XU, Dong-ning LIU. Time/Cost Trade-off Problem in Decentralized Multi-project Scheduling [J]. Chinese Journal of Management Science, 2023, 31(9): 62-72. |
| [10] | ZHAI Meng-yue, WANG Zheng, LI Yan-tong, HU Xiang-pei. Research on the Problem of Allocating Commodity Storage Locations in a Mobile-rack Storage System [J]. Chinese Journal of Management Science, 2023, 31(3): 167-176. |
| [11] | GE Xian-long, WEN Peng-zhe, XUE Gui-qin. Two-echelon Dynamic Vehicle Routing Problem with Request Forecasting [J]. Chinese Journal of Management Science, 2022, 30(8): 210-220. |
| [12] | HUANG Xiao-ling, CHEN Huan-ping, GAO Xiao-nan, WANG Dan, LIU Jin-ping, CHEN Ji-hong. Deliverysplit Milkrun and Supplyhub Collaborate to Optimize Automobiles Parts Inbound logistics [J]. Chinese Journal of Management Science, 2022, 30(7): 59-68. |
| [13] | YAN Rui, CHEN Li-shuang, ZHU Xiao-ning, TIAN Hao-tong, WEN Ya, ZHANG Qun. Research on Vehicle Routing Problem with Truck and Drone Considering Regional Restriction [J]. Chinese Journal of Management Science, 2022, 30(5): 144-155. |
| [14] | MA Zhi-qiang, XU Xiao-feng, HE Zheng-wen, WANG Neng-min. Robust Scheduling Optimization of Project Resources with Activity Splitting under Complex and Uncertain Environments [J]. Chinese Journal of Management Science, 2022, 30(3): 117-130. |
| [15] | ZHEN Lu, TAN Zhe-yi, XIAO Li-yang, MA Cheng-le. Research on Parcel Sorting Optimization Model and Algorithm for Double-layer Automatic Sorting Systems [J]. Chinese Journal of Management Science, 2021, 29(7): 171-180. |
| Viewed | ||||||
|
Full text |
|
|||||
|