Chinese Journal of Management Science ›› 2025, Vol. 33 ›› Issue (6): 85-95.doi: 10.16381/j.cnki.issn1003-207x.2023.0374
Previous Articles Next Articles
Sha Tao, Jing Jin, Jing Zhou(
)
Received:2023-03-06
Revised:2023-09-01
Online:2025-06-25
Published:2025-07-04
Contact:
Jing Zhou
E-mail:jzhou@nju.edu.cn
CLC Number:
Sha Tao,Jing Jin,Jing Zhou. The Integrated Optimization Project Scheduling and Personnel Assignment Considering Online-Onsite Collaboration[J]. Chinese Journal of Management Science, 2025, 33(6): 85-95.
"
| 案例组 | 平均总工期(单位:天) | 平均运行时间(单位:秒) | GAP | ||
|---|---|---|---|---|---|
| Gurobi | GA | Gurobi | GA | ||
| J10_1 | 22 | 22 | 36.48 | 30.02 | 0 |
| J10_2 | 24.7 | 26.7 | 30.39 | 29.32 | 0.08 |
| J10_3 | 16 | 19 | 26.09 | 26.71 | 0.19 |
| J10_4 | 16.3 | 17 | 31.03 | 27.54 | 0.04 |
| J10_5 | 13 | 13 | 19.69 | 26.13 | 0 |
| J20_1 | 18 | 19.7 | 130.77 | 68.62 | 0.09 |
| J20_2 | 28 | 29 | 111.52 | 56.68 | 0.04 |
| J20_3 | 22 | 24 | 126.98 | 56.93 | 0.09 |
| J20_4 | 24 | 25 | 108.25 | 52.99 | 0.04 |
| J20_5 | 21 | 23 | 133.78 | 56.47 | 0.10 |
| J301_1 | 53 | 57 | 4608.39 | 170.51 | 0.08 |
| J301_2 | 42 | 43 | 539.20 | 105.67 | 0.02 |
| J301_3 | 43 | 43 | 468.25 | 107.96 | 0 |
| J301_4 | 55 | 61 | 1158.51 | 118.80 | 0.11 |
| J301_5 | 31 | 31 | 451.56 | 108.21 | 0 |
| 1 | Pritsker A A B, Waiters L J, Wolfe P M. Multiproject scheduling with limited resources: A zero-one programming approach[J]. Management Science, 1969, 16(1): 93-108. |
| 2 | 何正文, 刘人境, 胡信布. 基于合同双方交互作用的项目调度优化[J]. 管理科学学报, 2014, 17(8):48-59. |
| He Z W, Liu R J, Hu X B. Project scheduling optimization based on interaction between two parties of contracts[J]. Journal of Management Sciences in China, 2014, 17(8):48-59. | |
| 3 | 张静文, 乔传卓, 刘耕涛. 基于鲁棒性的关键链二次资源冲突消除策略[J]. 管理科学学报, 2017, 20(3):106-119. |
| Zhang J W, Qiao C Z, Liu G T. Strategy to eliminate the second resource conflicts in critical chain method based on robustness[J]. Journal of Management Sciences in China, 2017, 20(3):106-119. | |
| 4 | Néron E. Lower bounds for the multi-skill project scheduling problem[C]//Proceedings of The Eighth International Workshop on Project Management and Scheduling, Valencia, Spain, April 3-5 , European Union of Operational Research Societies (EURO) & Universidad de Valencia, 2002: 274-277. |
| 5 | 陈蓉, 梁昌勇, 叶春森. 考虑学习效应的新产品R&D项目组合调度模型研究[J]. 管理工程学报, 2016, 30(2):101-107. |
| Chen R, Liang C Y, Ye C S. A new product R&D project portfolio scheduling model considering learning effect[J]. Journal of Industrial Engineering and Engineering Management, 2016, 30(2):101-107. | |
| 6 | Joshi D, Mittal M L, Sharma M K, et al. An effective teaching-learning-based optimization algorithm for the multi-skill resource-constrained project scheduling problem[J]. Journal of Modelling in Management, 2019, 14(4): 1064-1087. |
| 7 | Kazemipoor H, Tavakkoli-Moghaddam R, Shahnazari-Shahrezaei P, et al. A differential evolution algorithm to solve multi-skilled project portfolio scheduling problems[J]. The International Journal of Advanced Manufacturing Technology, 2013, 64(5): 1099-1111. |
| 8 | Bellenguez O, Néron E. Lower bounds for the multi-skill project scheduling problem with hierarchical levels of skills[M]//Burke E, Trick M. Practice and Theory of Automated Timetabling V.Berlin,Heidelberg: Springer Berlin Heidelberg, 2005: 229-243. |
| 9 | Javanmard S, Afshar-Nadjafi B, Taghi Akhavan Niaki S. A bi-objective model for scheduling of multiple projects under multi-skilled workforce for distributed load energy usage[J].Operational Research,2022,22: 2245-2280. |
| 10 | Brusco M J, Johns T R. Staffing a multiskilled workforce with varying levels of productivity: An analysis of cross‐training policies[J]. Decision Sciences, 1998, 29(2): 499-515. |
| 11 | Maghsoudlou H, Afshar-Nadjafi B, Niaki S T A. A multi-objective invasive weeds optimization algorithm for solving multi-skill multi-mode resource constrained project scheduling problem[J]. Computers & Chemical Engineering, 2016, 88: 157-169. |
| 12 | Chen R, Liang C Y, Gu D X, et al. A competence-time-quality scheduling model of multi-skilled staff for IT project portfolio[J]. Computers & Industrial Engineering, 2020, 139: 106183. |
| 13 | 陈蓉, 梁昌勇, 叶春森,等. 考虑随机离职的新产品研发项目组合多技能员工调度模型[J]. 系统工程理论与实践, 2018, 38(1):164-176. |
| Chen R, Liang C Y, Ye C S, et al. A multi-skilled staff scheduling model for new product R&D project portfolio under stochastic turnover[J].Systems Engineering-Theory & Practice, 2018,38(1):164-176. | |
| 14 | Li Q, Sun Q S, Tao S, et al. Multi-skill project scheduling with skill evolution and cooperation effectiveness[J]. Engineering, Construction and Architectural Management, 2019, 27(8): 2023-2045. |
| 15 | Snauwaert J, Vanhoucke M. A new algorithm for resource-constrained project scheduling with breadth and depth of skills[J]. European Journal of Operational Research, 2021, 292(1): 43-59. |
| 16 | 马咏,何正文,郑维博.基于柔性资源约束的前摄性项目调度优化研究[J].中国管理科学, 2020, 28(7):220-230. |
| Ma Y, He Z W, Zheng W B. Proactive project scheduling optimization based on flexible resource constraint[J]. Chinese Journal of Management Science, 2020, 28(7):220-230. | |
| 17 | 于懿宁, 徐哲, 刘东宁. 考虑多技能人力资源的分布式多项目调度问题[J]. 系统工程理论与实践, 2020, 40(11):2921-2933. |
| Yu Y N, Xu Z, Liu D N. Distributed multi-project scheduling problem with multi-skilled staff[J]. Systems Engineering-Theory & Practice, 2020, 40(11):2921-2933. | |
| 18 | 王莹莹, 吴立云. 基于改进NSGA-II的多项目多技能人力资源调度研究[J]. 工业工程, 2021, 24(3):130-138. |
| Wang Y Y, Wu L Y. A research on multi-project multi-skill human resource scheduling based on improved NSGA-II[J]. Industrial Engineering Journal, 2021, 24(3):130-138. | |
| 19 | Valls V, Pérez Á, Quintanilla S. Skilled workforce scheduling in service centres[J]. European Journal of Operational Research, 2009, 193(3): 791-804. |
| 20 | Gutiérrez J H, Astudillo C A, Ballesteros-Pérez P, et al. The multiple team formation problem using sociometry[J]. Computers & Operations Research, 2016, 75: 150-162. |
| 21 | Shadrokh S, Kianfar F. A genetic algorithm for resource investment project scheduling problem, tardiness permitted with penalty[J]. European Journal of Operational Research, 2007, 181(1):86-101. |
| [1] | Baofeng Tian, Jingwen Zhang, Lubo Li, Junjie Chen. Integrated Resource-constrained Project Scheduling and Material Ordering Problem with Limited Storage Space [J]. Chinese Journal of Management Science, 2025, 33(8): 144-155. |
| [2] | Xiao Cui, Zhengwen He, Nengmin Wang. Optimization of Reactive Project Scheduling with Stochastic Resource Requirements Considering Information Handling Input [J]. Chinese Journal of Management Science, 2025, 33(8): 218-229. |
| [3] | Wuliang Peng, Xuejun Lin. A Dynamic Reactive Scheduling Method for the Resource Constrained Project Scheduling Problem [J]. Chinese Journal of Management Science, 2025, 33(7): 200-209. |
| [4] | Song Xue, Xu Chen, Chao Li, Jingchun Feng. Research on Miniature Multi-Project Scheduling of Service Project Enterprises Considering the Evolution of Human Resources Skills [J]. Chinese Journal of Management Science, 2025, 33(6): 96-104. |
| [5] | Lili Zhang, Zhengrui Chen, Yang Yang, Shi Dan. One-to-many “Personnel-task” Assignment Method for Maintenance Project of Hazardous Chemicals Production Equipment Considering Complexity [J]. Chinese Journal of Management Science, 2025, 33(4): 175-184. |
| [6] | Yanting Wang, Weibo Zheng, Zhiqiang Ma, Zhengwen He. Robustness Threshold-based Max-NPV Project Scheduling Optimization on Different Clients’ Payment Modes [J]. Chinese Journal of Management Science, 2025, 33(4): 185-196. |
| [7] | Keyi Zhang, Yong Shi, Haixiang Guo, Yongzheng Sun. Optimal Decision-Making for Dispatching Emergency Supplies for Natural Disasters in Mountainous Areas Based on Truck-Drone Collaboration [J]. Chinese Journal of Management Science, 2025, 33(2): 150-160. |
| [8] | Yuanyuan Jiang, He Luo, Zhiwei Wu, Zhiming Cai, Guoqiang Wang. Research on the Joint Optimization of Procurement Planning and Supplier Selection for the Overseas Base of Manufacturing Enterprises [J]. Chinese Journal of Management Science, 2025, 33(10): 126-137. |
| [9] | Yidan He,Zhengwen He,Nengmin Wang,Zhiqiang Ma. Resource-constrained Max-NPV Multi-project Scheduling Optimization under Sharing Economy Environment [J]. Chinese Journal of Management Science, 2024, 32(9): 260-270. |
| [10] | Tieke Li,Yixuan Su,Wenxin Zhang,Bailin Wang. Interval Multi-objective Optimal Scheduling for Steelmaking-continuous Casting with Processing Time Uncertainty [J]. Chinese Journal of Management Science, 2024, 32(8): 95-106. |
| [11] | Zihao Chu,Zhe Xu,Dongning Liu. Model and Algorithm on Stochastic Scheduling Problem with Activity Overlapping [J]. Chinese Journal of Management Science, 2024, 32(7): 84-94. |
| [12] | Ling Zhang,Pengfei Gao,Lin Zhang. Research on Emergency Evacuation and Material Allocation Based on Deprivation Cost [J]. Chinese Journal of Management Science, 2024, 32(5): 187-195. |
| [13] | Zujun Ma, Yiran Wang. Optimal Location and Capacity of Pre-cooling Facilities Considering the First-Mile Loss of Fresh Agri-products [J]. Chinese Journal of Management Science, 2024, 32(2): 315-323. |
| [14] | Guiqin Xue, Xianlong Ge. Study on Two-stage Dynamic Vehicle Scheduling Optimization Considering the Proactive Category [J]. Chinese Journal of Management Science, 2024, 32(12): 164-172. |
| [15] | Xinyue Zhang,Peng Jin,Xiaoxuan Hu,Moning Zhu. Research on the Time-dependent Multi-depot Open Vehicle Routing Problem with Time Windows [J]. Chinese Journal of Management Science, 2024, 32(1): 146-157. |