	Chinese Journal of Management Science ›› 2025, Vol. 33 ›› Issue (10): 67-75.doi: 10.16381/j.cnki.issn1003-207x.2023.0245
Previous Articles Next Articles
					
													Qin Zhang1, Peng Xu2( ), Zhigeng Fang3, Sifeng Liu3
), Zhigeng Fang3, Sifeng Liu3
												  
						
						
						
					
				
Received:2023-02-15
															
							
																	Revised:2023-06-12
															
							
															
							
																	Online:2025-10-25
															
							
																	Published:2025-10-24
															
						Contact:
								Peng Xu   
																	E-mail:pengxu@smail.nju.edu.cn
																					CLC Number:
Qin Zhang,Peng Xu,Zhigeng Fang, et al. Periodic Maintenance Model of Parallel Critical System for Major Equipment to Prevent the Failure During the Operation Process[J]. Chinese Journal of Management Science, 2025, 33(10): 67-75.
 
													
													
"
| 10.0 | 0.385 | 117.567 | 0.550 | 89.569 | 0.724 | 78.825 | 0.893 | 74.590 | 
| 15.0 | 0.522 | 132.099 | 0.706 | 106.557 | 0.909 | 97.736 | 1.109 | 95.434 | 
| 20.0 | 0.665 | 143.909 | 0.863 | 121.115 | 1.095 | 114.403 | 1.328 | 114.151 | 
| 25.0 | 0.820 | 153.987 | 1.029 | 134.050 | 1.292 | 129.538 | 1.566 | 131.389 | 
| 30.0 | 0.995 | 162.839 | 1.211 | 145.792 | 1.514 | 143.522 | 1.843 | 147.503 | 
| 35.0 | 1.199 | 170.766 | 1.420 | 156.606 | 1.775 | 156.594 | 2.191 | 162.714 | 
| 40.0 | 1.448 | 177.964 | 1.669 | 166.665 | 2.106 | 168.915 | 2.686 | 177.172 | 
| 45.0 | 1.772 | 184.567 | 1.988 | 176.094 | 2.572 | 180.599 | 3.616 | 190.987 | 
 
													
													
"
| 10.0 | 0.900 | 149.072 | 1.052 | 122.464 | 1.194 | 107.458 | 1.327 | 98.396 | 
| 15.0 | 0.989 | 154.331 | 1.150 | 130.281 | 1.313 | 117.683 | 1.470 | 110.859 | 
| 20.0 | 1.090 | 159.568 | 1.259 | 138.005 | 1.444 | 127.692 | 1.624 | 122.934 | 
| 25.0 | 1.205 | 164.754 | 1.380 | 145.593 | 1.588 | 137.421 | 1.794 | 134.541 | 
| 30.0 | 1.339 | 169.853 | 1.517 | 152.996 | 1.749 | 146.803 | 1.985 | 145.603 | 
| 35.0 | 1.498 | 174.819 | 1.673 | 160.161 | 1.932 | 155.772 | 2.202 | 156.044 | 
| 40.0 | 1.687 | 179.600 | 1.853 | 167.029 | 2.143 | 164.260 | 2.455 | 165.792 | 
| 45.0 | 1.917 | 184.134 | 2.064 | 173.541 | 2.392 | 172.200 | 2.761 | 174.772 | 
| [1] | de Smidt-Destombes K S, van der Heijden M C, van Harten A. Availability of k-out-of- N systems under block replacement sharing limited spares and repair capacity[J]. International Journal of Production Economics, 2007, 107(2): 404-421. | 
| [2] | 陈曦. 基子RCM方法的高温气冷堆核电站电气设备维修策略改进[D]. 济南: 山东大学硕士学位论文, 2020. | 
| Chen X. Improvement of maintenance strategy for electrical equipment of HTR-PM based on RCM[D]. Jinan: Master Dissertation of Shandong University, 2020. | |
| [3] | 苏春, 周小荃. 基于有效年龄的风力机多部件维修优化[J].东南大学学报(自然科学版),2012, 42(6): 1100-1104. | 
| Su C, Zhou X Q. Maintenance optimization for multi-component of wind turbine based on effective age[J]. Journal of Southeast University (Natural Science Edition), 2012, 42(6): 1100-1104. | |
| [4] | 王红, 熊律, 杜维鑫, 等. 考虑故障风险的动车组部件预防性维护优化建模[J]. 机械工程学报, 2016, 52(24): 123-129. | 
| Wang H, Xiong L, Du W X, et al. Optimization of preventive maintenance for component of electric multiple unit with consideration of failure risk[J]. Journal of Mechanical Engineering, 2016, 52(24): 123-129. | |
| [5] | 陈童, 谢经伟. 面向预防性维修的两种失效竞争下多状态系统可靠性模型[J]. 系统工程理论与实践, 2020, 40(3): 807-816. | 
| Chen T, Xie J W. Reliability analysis of multi-state system with competing failure based on preventive maintenance[J]. Systems Engineering-Theory & Practice, 2020, 40(3): 807-816. | |
| [6] | Yang L, Ye Z S, Lee C G, et al. A two-phase preventive maintenance policy considering imperfect repair and postponed replacement[J]. European Journal of Operational Research, 2019, 274(3): 966-977. | 
| [7] | Ouaret S, Kenné J P, Gharbi A. Production and replacement policies for a deteriorating manufacturing system under random demand and quality[J]. European Journal of Operational Research, 2018, 264(2): 623-636. | 
| [8] | Schouten T N, Dekker R, Hekimoğlu M, et al. Maintenance optimization for a single wind turbine component under time-varying costs[J]. European Journal of Operational Research, 2022, 300(3): 979-991. | 
| [9] | Jiang R. A novel two-fold sectional approximation of renewal function and its applications[J]. Reliability Engineering & System Safety, 2020, 193: 106624. | 
| [10] | 张新生, 张平. 不完全维修下海底腐蚀管道剩余寿命预测[J].系统工程理论与实践, 2019, 39(11): 2984-2994. | 
| Zhang X S, Zhang P. Remaining useful life prediction of corroded submarine pipelines under imperfect maintenance[J]. Systems Engineering-Theory & Practice, 2019, 39(11): 2984-2994. | |
| [11] | Zhao X, Cai J, Mizutani S, et al. Preventive replacement policies with time of operations, mission durations, minimal repairs and maintenance triggering approaches[J].Journal of Manufacturing Systems,2021,61: 819-829. | 
| [12] | Zhang Q, Fang Z, Cai J. Extended block replacement policies with mission durations and maintenance triggering approaches[J]. Reliability Engineering & System Safety, 2021, 207: 107399. | 
| [13] | Zhang Q, Fang Z, Cai J. Preventive replacement policies with multiple missions and maintenance triggering approaches[J]. Reliability Engineering & System Safety, 2021, 213: 107691. | 
| [14] | Peng R, He X, Zhong C, et al. Preventive maintenance for heterogeneous parallel systems with two failure modes[J]. Reliability Engineering & System Safety, 2022, 220: 108310. | 
| [15] | Barros A, Grall A, Berenguer C. Joint modelling and optimization of monitoring and maintenance performance for a two-unit parallel system[J]. Proceedings of the Institution of Mechanical Engineers, Part O: Journal of Risk and Reliability, 2007, 221(1): 1-11. | 
| [16] | 徐智斌. 船舶电站冗余控制系统设计及可靠性分析[D]. 大连: 大连海事大学硕士学位论文, 2020. | 
| Xu Z B. Design and reliability analysis of redundancy control system of marine power station[D]. Dalian: Master Dissertation of Dalian Maritime University, 2020. | |
| [17] | 李京峰, 陈云翔, 项华春, 等. 考虑随机冲击影响的多部件系统视情维修与备件库存联合优化[J]. 系统工程与电子技术, 2022, 44(3): 875-883. | 
| Li J F, Chen Y X, Xiang H C, et al. Joint optimization of condition-based maintenance and spare part inventory for multi-component system considering random shock effect[J]. Systems Engineering and Electronics, 2022, 44(3): 875-883. | |
| [18] | 杨建华, 韩梦莹. 视情维修条件下k/N(G)系统备件供需联合优化[J]. 系统工程与电子技术, 2019, 41(9): 2148-2156. | 
| Yang J H, Han M Y. Joint optimization of spare parts supply-demand for k/N(G) system under condition-based maintenance[J]. Systems Engineering and Electronics, 2019, 41(9): 2148-2156. | |
| [19] | 李美娜, 孟宪云, 李晋星, 等. 基于休假时间和基准可靠度的冷贮备二维预防维修策略[J]. 系统科学与数学, 2017, 37(11): 2281-2292. | 
| Li M N, Meng X Y, Li J X, et al. The two dimensional preventive maintenance strategy for a cold standby system based on vacation and critical reliability[J]. Journal of Systems Science and Mathematical Sciences, 2017, 37(11): 2281-2292. | |
| [20] | 杨天枢, 高文科. 基于拓展几何过程的冷贮备系统维修策略优化[J]. 计算机集成制造系统, 2022, 28(1): 84-92. | 
| Yang T S, Gao W K. Optimization of maintenance policy for cold standby system based on extended geometric process[J]. Computer Integrated Manufacturing Systems, 2022, 28(1): 84-92. | |
| [21] | Safaei F, Châtelet E, Ahmadi J. Optimal age replacement policy for parallel and series systems with dependent components[J]. Reliability Engineering & System Safety, 2020, 197: 106798. | 
| [22] | Nakagawa T. Random maintenance policies[M]. London: Springer, 2014. | 
| [23] | Eryilmaz S. A Note on optimization problems of a parallel system with a random number of units[J]. International Journal of Reliability Quality & Safety Engineering,2017,24(5): 1750022. | 
| [24] | Yusuf I. Reliability modelling of a parallel system with a supporting device and two types of preventive maintenance[J].International Journal of Operational Research, 2016, 25(3): 269. | 
| [25] | Dong W, Liu S, Cao Y, et al. Reliability modeling and optimal random preventive maintenance policy for parallel systems with damage self-healing[J]. Computers & Industrial Engineering, 2020, 142: 106359. | 
| [1] | Guiqin Xue, Xianlong Ge. Study on Two-stage Dynamic Vehicle Scheduling Optimization Considering the Proactive Category [J]. Chinese Journal of Management Science, 2024, 32(12): 164-172. | 
| [2] | Zheng Wang,Peng Lu,Xiangpei Hu. Method of Locating Racks in Mobile-Rack Warehousing System [J]. Chinese Journal of Management Science, 2024, 32(8): 84-94. | 
| [3] | Tieke Li,Yixuan Su,Wenxin Zhang,Bailin Wang. Interval Multi-objective Optimal Scheduling for Steelmaking-continuous Casting with Processing Time Uncertainty [J]. Chinese Journal of Management Science, 2024, 32(8): 95-106. | 
| [4] | Guohua Wu. Based on Hub-Spoke Network a Practice Heuristic Algorithm Applied to Airline Fleet Assignment [J]. Chinese Journal of Management Science, 2024, 32(1): 158-167. | 
| [5] | Hai-yu WANG. 
														
															Economic-statistical Optimization Design of Dynamic | 
| [6] | ZHAI Meng-yue, WANG Zheng, LI Yan-tong, HU Xiang-pei. Research on the Problem of Allocating Commodity Storage Locations in a Mobile-rack Storage System [J]. Chinese Journal of Management Science, 2023, 31(3): 167-176. | 
| [7] | LIU Lang, , WANG Hui, HUANG Dong-hong. The Buy-back Contract of Supplier Risk Aversion under the Asymmetric Information of Sales Cost [J]. Chinese Journal of Management Science, 2023, 31(1): 158-167. | 
| [8] | WU Jiang-hua, JIANG Fan. Vertical Information Acquisition and Horizontal Information Sharing Strategy in a Supply Chain [J]. Chinese Journal of Management Science, 2021, 29(8): 161-173. | 
| [9] | CAO Xiao-ning, WANG Yong-ming, XUE Fang-hong, LIU Xiao-bing. Coordination Strategies for Dual-channel Supply Chain of Fresh Agricultural Products Considering the Fresh-keeping Effort of Supplier [J]. Chinese Journal of Management Science, 2021, 29(3): 109-118. | 
| [10] | LIU Lang, WU Shuang-sheng, SHI Wen-qiang. Research on Emergency Quantity Discount Contract with Stochastic Price under Asymmetric Information [J]. Chinese Journal of Management Science, 2018, 26(3): 169-176. | 
| [11] | ZHANG Han-jiang, YU Hua-ying, LI Cong-ying. Incentive Contract Design and Optimization Of Government Subsidies Policy in the Closed-loop Supply Chain [J]. Chinese Journal of Management Science, 2016, 24(8): 71-78. | 
| [12] | XING Xi-wen, MAO Jun, ZHANG Rui, JIN Zhi-hong. Optimization of Container Loading/unloading Integrated Scheduling in a Container Terminal Based on Hybrid Flowshop [J]. Chinese Journal of Management Science, 2014, 22(10): 97-105. | 
| [13] | JIN Peng, ZUO Chun-rong, YANG Shan-lin, MA Hua-wei. Cutting Stock Problem and Transportation Problem Collaboration Optimization Modeling [J]. Chinese Journal of Management Science, 2013, (2): 91-97. | 
| [14] | LIU Chun-ling, LI Ji-zi, MENG Bo. Research on H∞ Control of Bullwhip in Cluster Supply Chains Based on Cooperation between Two Single Chains [J]. Chinese Journal of Management Science, 2007, 15(1): 41-46. | 
| [15] | LIU Bin, HE Jian-min, CAO Hui-yu. Rebuilding PSG Fuzzy Decision-making System Using SVD Method [J]. Chinese Journal of Management Science, 2005, (3): 103-107. | 
| Viewed | ||||||
| Full text |  | |||||
| Abstract |  | |||||
| 
 | ||