中国管理科学 ›› 2026, Vol. 34 ›› Issue (10): 175-185.doi: 10.16381/j.cnki.issn1003-207x.2024.2109

• • 上一篇    

基于机器学习的场地受限型项目调度与物料订购集成优化

田宝峰1, 张静文2(), 陈志2   

  1. 1.太原理工大学经济与管理学院,山西 太原 030024
    2.西北工业大学管理学院,陕西 西安 710072
  • 收稿日期:2024-11-23 修回日期:2025-05-10 出版日期:2026-10-25 发布日期:2026-10-09
  • 通讯作者: 张静文 E-mail:zhangjingwen@nwpu.edu.cn
  • 基金资助:
    国家自然科学基金项目(71971173);国家自然科学基金项目(72201209);山西省基础研究计划项目(202503021212021);山西省重点实验室开放基金项目(2025-ZZ-05)

An Automatic Algorithm Recommendation Approach for the Project Scheduling and Material Ordering Problem with Site Space Constraints Through Machine Learning

Baofeng Tian1, Jingwen Zhang2(), Zhi Chen2   

  1. 1.College of Economics and Management,Taiyuan University of Technology,Taiyuan 030024,China
    2.School of Management,Northwestern Polytechnical University,Xi’an 710072,China
  • Received:2024-11-23 Revised:2025-05-10 Online:2026-10-25 Published:2026-10-09
  • Contact: Jingwen Zhang E-mail:zhangjingwen@nwpu.edu.cn

摘要:

施工场地受限下,活动进度与物料供应之间的精准协同是建筑工程项目顺畅执行的关键。本文从协同优化角度探究场地空间受限下的项目调度与物料订购集成优化问题,旨在通过集成决策活动进度安排和物料订购方案最小化项目总成本。首先,抽象并表达活动进度与物料订购之间的动态依赖关系,构建包含库存平衡式的集成优化模型;其次,结合模型特征设计改进的串行调度方案生成机制,进而开发并测试四种元启发式求解算法;再次,基于大规模算例上各算法的性能测试数据,采用6种机器学习技术训练算例特征与最佳算法之间的映射关系,从而构建了可为每个算例针对性地选择最佳求解算法的自动推荐方法。最后,通过大规模数值实验验证集成优化模型和算法的有效性。实验结果表明:基于随机森林的算法自动推荐方法在准确率和求解质量上优于其他单一算法和其他算法推荐方法。研究发现,在场地空间制约下,单位物料存储成本的增加对项目总成本的恶化效应更显著。

关键词: 项目调度, 物料订购, 集成优化模型, 机器学习, 算法推荐

Abstract:

The implementation of construction projects involves multiple spaces such as construction sites and prefabricated component manufacturers. How to realize the coordination between on-site activity scheduling and off-site material supply is critical to ensure the smooth execution of these projects. Meanwhile, the cramped site space furtherly renders the parallel execution of activities and limits the materials ordering plan through warehouse capacity. In order to solve the above practical dilemmas, the integrated optimization problem of project scheduling and material procurement under the limited space is explored is investigated in this paper.According to practical scenarios of construction projects with limited site space, the considered project scheduling and material ordering problem is defined. On this basis, considering the precedence relationships between activities, resource availability, inventory dynamic balance equations and site space constraints, the project scheduling and material ordering model with site space constraints is formulated. Through concurrently optimizing activity timetables and material ordering plan, the integrated model aims to minimize the total project cost.In order to solve the proposed problem, the complexity of the problem is analyzed. Based on the NP-hard characteristics of the problem, an algorithm automatic recommendation approach embedded with four meta-heuristics is developed using machine learning. Firstly, an improved serial scheduling generation scheme is proposed based on the problem structure, and four meta-heuristic algorithms are accordingly designed. Secondly, based on the extracted 91 instance features, the performance of five machine learning algorithms is tested, and the decision tree algorithms is selected to build the algorithm recommendation model due to its highest accuracy. Finally, the model parameters that make the approach perform best are determined by grid search method.To verify the effectiveness of the proposed method, large-scale numerical experiments are carried out based on the instances generated by ProGen and PSPLIB. The effectiveness of the proposed integrated model is verified by comparing with the independent model. The superiority the of developed automatic algorithm recommendation approach is also proved. Besides, comparative experiments among CPLEX, the proposed recommendation approach and other algorithms are set up, and experimental results demonstrate that the algorithm recommendation method based on random forest behaves best on accuracy and solution quality.The solution framework of the PSMOP is constructed by constructing an automatic algorithm recommendation approach embedded with multiple meta-heuristics. Meanwhile, the integrated decision making on both project scheduling and material ordering can provide more comprehensive decision supports for project managers. Moreover, reference values for the research on construction project management is provided.

Key words: project scheduling, material ordering, integrated optimization model, machine learning, algorithm recommendation