甲供资源约束条件下南水北调工程项目群工期-费用优化模型研究

丰景春1,3, 朱晓婧1, 李明1, 张可1,2, 薛松1   

  1. 1. 河海大学商学院项目管理研究所, 江苏 南京 211100;
    2. 国际河流研究中心, 江苏 南京 211100;
    3. 江苏省"世界水谷"与水生态文明协同创新中心, 江苏 南京 211100
  • 收稿日期:2017-08-27 修回日期:2017-12-27 出版日期:2019-01-20 发布日期:2019-03-25
  • 通讯作者: 朱晓婧(1994-),女(汉族),江苏江阴人,河海大学商学院硕士研究生,研究方向:工程管理与项目管理,E-mail:2514615616@qq.com. E-mail:2514615616@qq.com
  • 基金资助:

    国家社会科学基金重点资助项目(14AZD024);国家社会科学基金资助项目(17BGL156);国家社会科学基金青年项目(15CJL023)

Duration-Cost Optimization Model of Program of South-to-North Water Diversion Project under Restriction of Resources Supplied by Employer

FENG Jing-chun1,3, ZHU Xiao-jing1, LI Ming1, ZHANG Ke1,2, XUE Song1   

  1. 1. Hohai University, Business School, Institute of Project Management, Nanjing 211100, China;
    2. International River Research Centre, Nanjing 211100, China;
    3. Jiangsu Provincial Collaborative Innovation Centre of World Water Valley and Water Ecological Civilization, Nanjing 211100, China
  • Received:2017-08-27 Revised:2017-12-27 Online:2019-01-20 Published:2019-03-25

摘要: 在研究项目群工期—费用优化问题时,首先剖析了项目群工期—费用优化机理。然后建立了甲供资源约束条件下项目群实施前的工期—费用优化模型,对初始网络计划进行优化,使业主支付款净现值最小。但由于项目群中各合同项目间存在资源竞争和工期冲突等矛盾,可能引起某一合同项目的工期延误。基于此,构建项目群实施过程中的工期—费用优化模型,对实施前优化后的网络计划进行动态调整。最后结合南水北调某X项目群对比了不同工期—费用优化下的结果。结果显示:两阶段的项目群工期—费用优化可实现项目群的费用控制目标,为项目经理确定项目群中各合同项目的起始时间提供依据。

关键词: 项目群, 资源约束, 南水北调工程, 资金的时间价值, 工期-费用权衡

Abstract: Since 2015, the National Development and Reform Commission, the Ministry of Foreign Affairs and the Ministry of Commerce jointly released the Vision and Actions for Promoting the Building of the Belt and Road Initiative. Afterwards, more and more large and medium-sized construction projects are undertaken at home and abroad. In order to make sure that the three control objectives of duration, cost and quality can be implemented successfully, the program management of large and medium-sized construction projects came into being. Based on this, this paper focuses on the duration-cost optimization of program, and establishes a time-cost optimization model before the implementation of the program under the condition of resource constraints, then the initial network plan is optimized. After that, taking the penalty fee (f(T#em/em#)) into consideration, which is proposed by the employer to the contractor due to the delay of the bidding section on the non-critical path, the duration-cost optimization model during the implementation of the program is constructed, then the optimized network plan before implementation is dynamically adjusted, so that the net present value of the employer's payment can be minimized. Finally, the results of different duration-cost optimization are illustrated by an example:program X of South-to-North Water Diversion. The results show that the two-stage proposed model can actualize the optimization of program's cost control objective and provide the basis for the employer to determine the starting time of each bidding section in the program. In this way, the program optimization theory can be further improved.

Key words: program, restriction of resources, South-to-North Water Diversion Project, NPV(Net Present Value), duration-cost trade-off