Chinese Journal of Management Science ›› 2024, Vol. 32 ›› Issue (7): 84-94.doi: 10.16381/j.cnki.issn1003-207x.2021.0481
Previous Articles Next Articles
Zihao Chu1,Zhe Xu2(
),Dongning Liu3
Received:2021-03-10
Revised:2022-03-16
Online:2024-07-25
Published:2024-08-07
Contact:
Zhe Xu
E-mail:xuzhebuaa@163.com
CLC Number:
Zihao Chu,Zhe Xu,Dongning Liu. Model and Algorithm on Stochastic Scheduling Problem with Activity Overlapping[J]. Chinese Journal of Management Science, 2024, 32(7): 84-94.
"
| cnub | Ave Gap (%) | ||||||||
|---|---|---|---|---|---|---|---|---|---|
| U1 | U2 | Exp | B1 | B2 | |||||
| 20 | 0.6 | 0.01 | 50 | 1 | 69.13 | 78.50 | 95.51 | 69.33 | 80.76 |
| 20 | 0.7 | 0.05 | 100 | 5 | 67.71 | 78.06 | 95.45 | 68.89 | 80.53 |
| 20 | 0.8 | 0.1 | 200 | 10 | 68.48 | 78.09 | 95.21 | 68.92 | 80.29 |
| 40 | 0.6 | 0.01 | 100 | 5 | 68.21 | 77.81 | 94.68 | 68.33 | 79.86 |
| 40 | 0.7 | 0.05 | 200 | 10 | 67.90 | 78.06 | 94.86 | 68.61 | 79.98 |
| 40 | 0.8 | 0.1 | 50 | 1 | 68.47 | 78.24 | 95.24 | 68.50 | 80.24 |
| 60 | 0.6 | 0.05 | 50 | 10 | 67.75 | 77.38 | 94.60 | 68.21 | 79.65 |
| 60 | 0.7 | 0.1 | 100 | 1 | 68.16 | 77.92 | 94.64 | 68.81 | 80.35 |
| 60 | 0.8 | 0.01 | 200 | 5 | 67.68 | 78.18 | 94.83 | 68.62 | 80.07 |
| 80 | 0.6 | 0.1 | 200 | 5 | 68.26 | 77.80 | 94.95 | 68.37 | 80.23 |
| 80 | 0.7 | 0.01 | 50 | 10 | 67.69 | 77.29 | 94.12 | 68.00 | 79.14 |
| 80 | 0.8 | 0.05 | 100 | 1 | 68.56 | 78.23 | 94.68 | 68.73 | 80.43 |
| 100 | 0.6 | 0.05 | 200 | 1 | 69.30 | 77.96 | 94.65 | 69.01 | 79.98 |
| 100 | 0.7 | 0.1 | 50 | 5 | 67.84 | 77.53 | 94.79 | 68.23 | 79.32 |
| 100 | 0.8 | 0.01 | 100 | 10 | 68.08 | 77.65 | 94.61 | 68.57 | 79.41 |
| 120 | 0.6 | 0.1 | 100 | 10 | 68.28 | 77.48 | 94.33 | 68.73 | 79.60 |
| 120 | 0.7 | 0.01 | 200 | 1 | 69.11 | 77.95 | 95.04 | 69.63 | 80.14 |
| 120 | 0.8 | 0.05 | 50 | 5 | 67.86 | 77.64 | 94.38 | 68.38 | 79.68 |
"
| 算法 | schedules | Ave Gap (%) | ||||
|---|---|---|---|---|---|---|
| U1 | U2 | Exp | B1 | B2 | ||
| ABGA | 5000 | 51.49 | 78.65 | 120.22 | - | - |
| 25000 | 49.63 | 75.38 | 116.83 | - | - | |
| ABGR | 5000 | 46.84 | 72.58 | 114.42 | 47.17 | 75.97 |
| 25000 | 45.21 | 70.95 | 112.37 | 45.60 | 74.17 | |
| PPGA | 5000 | 48.86 | 58.91 | 76.03 | 49.01 | 58.82 |
| 25000 | 47.21 | 58.07 | 74.56 | 47.25 | 57.95 | |
| RB-EDA | 5000 | 47.29 | 56.54 | 72.50 | 47.65 | 58.29 |
| 25000 | 46.66 | 56.07 | 72.05 | 47.04 | 57.82 | |
| GP-H | 5000 | 46.71 | 55.95 | 71.71 | 46.87 | 55.95 |
| 25000 | 44.98 | 55.37 | 71.29 | 45.12 | 55.42 | |
| RB-LFT | 1 | 48.05 | 55.59 | 70.95 | 48.05 | 55.56 |
| RB-SLFT | 1 | 48.04 | 55.48 | 70.76 | 48.04 | 55.45 |
| GA-Rollout | 5000 | 45.13 | 54.04 | 69.03 | 45.59 | 55.61 |
| 25000 | 44.02 | 53.20 | 68.43 | 44.42 | 54.72 | |
| 1 | Roemer T A, Ahmadi R. Concurrent crashing and overlapping in product development[J]. Operations Research, 2004, 52(4): 606-622. |
| 2 | Wang J, Lin Y I. An overlapping process model to assess schedule risk for new product development[J]. Computers & Industrial Engineering,2009, 57(2): 460-474. |
| 3 | Dehghan R, Hazini K, Ruwanpura J. Optimization of overlapping activities in the design phase of construction projects[J]. Automation in Construction,2015, 59: 81-95. |
| 4 | Cho S, Eppinger S D. A simulation-based process model for managing complex design projects[J]. IEEE Transactions on Engineering Management,2005, 52(3): 316-328. |
| 5 | 李洪波,徐哲. 考虑活动随机重叠和资源冲突的复杂产品开发流程仿真建模[J]. 系统工程与电子技术,2012, 34(7): 1412-1418. |
| Li H B, Xu Z. Simulation modeling of complex product development process considering stochastic activities overlap and resource conflict[J]. Systems Engineering and Electronics, 2012, 34(7): 1412-1418. | |
| 6 | Chu Z, Xu Z, Xie F. Experimental evaluation of overlapping strategy for the multimode resource-constrained project scheduling problem[J]. Arabian Journal for Science and Engineering, 2019, 44(3): 2503-2517. |
| 7 | 初梓豪,徐哲.活动重叠对缩短资源受限项目工期有效性研究[J].系统工程理论与实践,2019, 39(9): 2388-2397. |
| Chu Z H, Xu Z. Research on the effectiveness of activities overlapping in reducing project duration under resource constrained condition[J]. Systems Engineering - Theory & Practice, 2019, 39(9): 2388-2397. | |
| 8 | 于静,徐哲,李洪波. 带有活动重叠的资源受限项目调度问题建模与求解[J]. 系统工程理论与实践, 2015, 35(5): 1236-1245. |
| Yu J, Xu Z, Li H B. Modeling and solving the resource-constrained project scheduling problem with activity overtlapping[J].Systems Engineering-Theory & Practice, 2015, 35(5): 1236-1245. | |
| 9 | 于静,徐哲,谢芳. 活动重叠模式与资源约束下的项目调度优化[J]. 管理科学学报, 2017, 20(9): 36-45. |
| Yu J, Xu Z, Xie F. Project scheduling optimization with overlapping modes and resource constraints[J]. Journal of Management Sciences in China, 2017, 20(9): 36-45. | |
| 10 | Chu Z, Xu Z, Li H. New heuristics for the RCPSP with multiple overlapping modes[J]. Computers & Industrial Engineering, 2019, 131: 146-156. |
| 11 | Ashtiani B, Leus R, Aryanezhad M. New competitive results for the stochastic resource-constrained project scheduling problem: Exploring the benefits of pre-processing[J]. Journal of Scheduling, 2011, 14(2): 157-171. |
| 12 | 王凌,郑环宇,郑晓龙. 不确定资源受限项目调度研究综述[J]. 控制与决策, 2014, 29(4): 577-584. |
| Wang L, Zheng H Y, Zheng X L. Survey on resource-constrained project scheduling under uncertainty[J]. Control & Decision, 2014, 29(4): 577-584. | |
| 13 | Radermacher F J. Cost-dependent essential systems of ES-strategies for stochastic scheduling problems[J]. Methods of Operations Research, 1981, 42: 17-31. |
| 14 | Igelmund G, Radermacher F J. Preselective strategies for the optimization of stochastic project networks under resource constraints[J].Networks,1983,13(1): 1-28. |
| 15 | Möhring R H, Stork F. Linear preselective policies for stochastic project scheduling[J]. Mathematical Methods of Operations Research, 2000, 52(3): 501-515. |
| 16 | Graham R L. Bounds on multiprocessing timing anomalies[J]. Siam Journal on Applied Mathematics, 1969, 17(2): 416-429. |
| 17 | Ballestín F. When it is worthwhile to work with the stochastic RCPSP?[J]. Journal of Scheduling, 2007, 10(3): 153-166. |
| 18 | Chen Z, Demeulemeester E, Bai S, et al. Efficient priority rules for the stochastic resource-constrained project scheduling problem[J]. European Journal of Operational Research, 2018, 270(3): 957-967. |
| 19 | Ashtiani B, Leus R, Aryanezhad M B. New competitive results for the stochastic resource-constrained project scheduling problem: Exploring the benefits of pre-processing[J]. Journal of Scheduling, 2011, 14(2): 157-171. |
| 20 | Rostami S, Creemers S, Leus R. New strategies for stochastic resource-constrained project scheduling[J]. Journal of Scheduling, 2018,21(3): 349-365. |
| 21 | Li H, Womer N K. Solving stochastic resource-constrained project scheduling problems by closed-loop approximate dynamic programming[J]. European Journal of Operational Research, 2015, 246(1): 20-33. |
| 22 | Creemers S. The preemptive stochastic resource-constrained project scheduling problem[J]. European Journal of Operational Research, 2019, 277(1): 238-247. |
| 23 | 夏宏青,焦健,褚嘉运,等. 基于改进GERT的任务过程时间特性建模分析方法[J]. 北京航空航天大学学报, 2020, 46(11): 2140-2148. |
| Xia H Q, Jiao J, Chu J Y, et al. Improved GERT based time characteristic modeling and analysis method for task process[J]. Journal of Beijing University of Aeronautics and Astronautics, 2020, 46(11): 2140-2148. | |
| 24 | Holland J H. Adaptation in natural and artificial systems[M]. USA: University of Michagan Press, 1992. |
| 25 | Hartmann S. A competitive genetic algorithm for resource-constrained project scheduling[J]. Naval Research Logistics, 1998, 45(7): 733-750. |
| 26 | Drexl A. Scheduling of project networks by job assignment[J]. Management Science, 1991, 37(12): 1590-1602. |
| 27 | Schirmer A, Riesenberg S. Parameterized heuristics for project scheduling-biased random sampling methods[D]. Germany: University Kiel, 1997. |
| 28 | Boctor F F. Resource-constrained project scheduling by simulated annealing[J]. International Journal of Production Research, 1996, 34(8): 2335-2351. |
| 29 | Alcaraz J, Maroto C. A robust genetic algorithm for resource allocation in project scheduling[J]. Annals of Operations Research, 2001, 102(1-4): 83-109. |
| 30 | Valls V, Ballestín F, Quintanilla S. A hybrid genetic algorithm for the resource-constrained project scheduling problem[J]. European Journal of Operational Research, 2008, 185(2): 495-508. |
| 31 | Bertsekas D, Tsitsiklis J N, Wu C. Rollout algorithms for combinatorial optimization[J]. Journal of Heuristics, 1997, 3(3): 245-262. |
| 32 | 谢芳,李洪波,柏庆国. 随机多模式资源受限项目调度[J].中国管理科学, 2022, 30(10): 155-164. |
| Xie F, Li H B, Bai Q G. Stochastic multi-mode resource-constrained project scheduling[J]. Chinese Journal of Management Science, 2022, 30(10): 155-164. | |
| 33 | Ballestín F, Leus R. Resource-constrained project scheduling for timely project completion with stochastic activity durations[J]. Production & Operations Management, 2009, 18(4): 459-474. |
| 34 | Li H, Demeulemeester E. A genetic algorithm for the robust resource leveling problem[J]. Journal of Scheduling, 2016, 19(1): 43-60. |
| 35 | Yassine A A, Mostafa O, Browning T R. Scheduling multiple, resource-constrained, iterative, product development projects with genetic algorithms[J]. Computers & Industrial Engineering, 2017, 107: 39-56. |
| 36 | Fang C, Kolisch R, Wang L, et al. An estimation of distribution algorithm and new computational results for the stochastic resource-constrained project scheduling problem[J]. Flexible Services & Manufacturing Journal, 2015, 27(4): 585-605. |
| [1] | Sha Tao, Jing Jin, Jing Zhou. The Integrated Optimization Project Scheduling and Personnel Assignment Considering Online-Onsite Collaboration [J]. Chinese Journal of Management Science, 2025, 33(6): 85-95. |
| [2] | Song Xue, Xu Chen, Chao Li, Jingchun Feng. Research on Miniature Multi-Project Scheduling of Service Project Enterprises Considering the Evolution of Human Resources Skills [J]. Chinese Journal of Management Science, 2025, 33(6): 96-104. |
| [3] | Lili Zhang, Zhengrui Chen, Yang Yang, Shi Dan. One-to-many “Personnel-task” Assignment Method for Maintenance Project of Hazardous Chemicals Production Equipment Considering Complexity [J]. Chinese Journal of Management Science, 2025, 33(4): 175-184. |
| [4] | Keyi Zhang, Yong Shi, Haixiang Guo, Yongzheng Sun. Optimal Decision-Making for Dispatching Emergency Supplies for Natural Disasters in Mountainous Areas Based on Truck-Drone Collaboration [J]. Chinese Journal of Management Science, 2025, 33(2): 150-160. |
| [5] | Yuanyuan Jiang, He Luo, Zhiwei Wu, Zhiming Cai, Guoqiang Wang. Research on the Joint Optimization of Procurement Planning and Supplier Selection for the Overseas Base of Manufacturing Enterprises [J]. Chinese Journal of Management Science, 2025, 33(10): 126-137. |
| [6] | Tieke Li,Yixuan Su,Wenxin Zhang,Bailin Wang. Interval Multi-objective Optimal Scheduling for Steelmaking-continuous Casting with Processing Time Uncertainty [J]. Chinese Journal of Management Science, 2024, 32(8): 95-106. |
| [7] | Ling Zhang,Pengfei Gao,Lin Zhang. Research on Emergency Evacuation and Material Allocation Based on Deprivation Cost [J]. Chinese Journal of Management Science, 2024, 32(5): 187-195. |
| [8] | Qing Yang,Yingxin Bi,Mingxing Chang,Tao Yao. The Impact of Knowledge Transfer among Overlapped Projects on the Program Clustering [J]. Chinese Journal of Management Science, 2024, 32(4): 261-270. |
| [9] | Zujun Ma, Yiran Wang. Optimal Location and Capacity of Pre-cooling Facilities Considering the First-Mile Loss of Fresh Agri-products [J]. Chinese Journal of Management Science, 2024, 32(2): 315-323. |
| [10] | Guiqin Xue, Xianlong Ge. Study on Two-stage Dynamic Vehicle Scheduling Optimization Considering the Proactive Category [J]. Chinese Journal of Management Science, 2024, 32(12): 164-172. |
| [11] | Xinyue Zhang,Peng Jin,Xiaoxuan Hu,Moning Zhu. Research on the Time-dependent Multi-depot Open Vehicle Routing Problem with Time Windows [J]. Chinese Journal of Management Science, 2024, 32(1): 146-157. |
| [12] | CHEN Xiao-hong, ZHOU Ming-hui, TANG Xiang-bo. Research on the Optimal Control Strategy for Pollution Reduction in Winter under the Constraints of Urban Air Quality Targets [J]. Chinese Journal of Management Science, 2023, 31(3): 1-9. |
| [13] | MA Zhi-qiang, XU Xiao-feng, HE Zheng-wen, WANG Neng-min. Robust Scheduling Optimization of Project Resources with Activity Splitting under Complex and Uncertain Environments [J]. Chinese Journal of Management Science, 2022, 30(3): 117-130. |
| [14] | FAN Hou-ming, TIAN Pan-jun, LV Ying-chun, ZHANG Yue-guang. Cross-dock Door Assignment and Vehicle Routing Problem of Considering Temporal-Spatial Distance [J]. Chinese Journal of Management Science, 2022, 30(2): 137-149. |
| [15] | LI Fei-fei, XU Zhe. Distributed Multi-project Stochastic Scheduling with Two-stage Coordination Mechanism of Resources Allocation [J]. Chinese Journal of Management Science, 2022, 30(12): 38-51. |
| Viewed | ||||||
|
Full text |
|
|||||
|
Abstract |
|
|||||
|
||