A Study on Emergency Plan Reconstruction With Resource Constraint

Expand
  • Institute of Policy and Management, Chinese Academy of Sciences, Beijing, China, 100190, China

Received date: 2014-07-30

  Revised date: 2016-09-01

  Online published: 2017-03-22

Abstract

On the basis of the expression by the introduction of the network plan technique,the emergency disposal processes are added with resource types, quantity, and completion time constraints. The way to generate resource scheduling program is explored by computer on-line reconstruction. To satisfy the disposal need of many types of emergencies concurrent or secondary contingency, the quantity limitation and time-window of total resources constraints are considered in the model. The steps, objectives and considerations of the development in resource scheduling scheme are analyzed, and the models both in parallel and mutually exclusive scenarios are constructed, a heuristic algorithm is designed, using the contingency plans for reconstruction of the sample in an airline.

Cite this article

SHI Biao, CHI Hong, QI Ming-liang, LI Jia-lian . A Study on Emergency Plan Reconstruction With Resource Constraint[J]. Chinese Journal of Management Science, 2017 , 25(1) : 117 -128 . DOI: 10.16381/j.cnki.issn1003-207x.2017.01.013

References

[1] 祁明亮, 池宏,等. 突发事件应急管理专项报告[M]//中国科学技术协会.2007-2008管理科学与工程学科发展报告, 北京:中国科学技术出版社,2008:104-123.

[2] 吴宗之, 刘茂. 重大事故应急预案分级、分类体系及其基本内容[M]. 中国安全科学学, 2003,13(1):15-18.

[3] 于瑛英,池宏. 基于网络计划的应急预案的可操作性研究[J]. 公共管理学报, 2007, 4(2):100-107.

[4] 于瑛英,池宏,高敏刚. 应急预案的综合评估研究[J]. 中国科技论坛, 2009,(02):88-92.

[5] Gelderman J, Bertsch V, Treitz M, et al. Multi-criteria decision support and evaluation of strategies for nuclear remediation management[J]. Omega, 2009, 37(1):238-251.

[6] 刘吉夫, 张盼娟, 陈志芬, 等. 我国自然灾害类应急预案评价方法研究(Ⅰ):完备性评价[J]. 中国安全科学学报, 2008, 18(2):5-11.

[7] 荣莉莉, 杨永俊. 一种基于知识供需匹配的预案应急能力评价方法[J]. 管理学报, 2009, 6(12):1643-1647, 1686.

[8] 李永海,樊治平,袁媛. 基于相似历史案例分析的突发事件应急方案生成方法[J]. 系统工程,2014,(4):76-81.

[9] 温志强.政府职能转变视域下的突发事件应急决策模式创新研究[J]. 管理世界,2016,(5):176-177.

[10] 池宏, 计雷, 谌爱群. 由突发事件引发的"动态博弈网络技术"的探讨[J],项目管理技术,2003,(1):12-14.

[11] 姚杰,计雷,池宏. 突发事件应急管理中大的动态博弈分析[J].管理评论,2005,17(3):46-50.

[12] Qi Mingliang, Chi Hong, Xu J G et.al. A study on selecting emergency counterplan in uncertainty situation[C]//Proceedings of 2008 International Conference on Management Science and Engineering Management,Chongqing, China,2008:711-716.

[13] Bryson K M, Millarb H, Josephc A, et al. Using formal MS/OR modeling to support disaster recovery planning[J]. European Journal of Operational Research, 2002,141(3):679-688.

[14] 王庆全,荣莉莉,于凯. 一种基于范畴论的应急决策概念建模方法[J],情报学报,2009,28(6):929-938.

[15] Qi Mingliang, Chi Hong,Ji Lei, et al. A study on the method for constituting an operable emergency plan[C]//Proceedings of The 3rd International Conference on Management and Service Science,Beijing, September 10-18,2009.

[16] 刘磊,池宏,邵雪焱,等. 预案管理中的重构问题研究[C]. 第四届国际应急管理论坛暨中国(双法)应急管理专业委员会第五届年会(ISEM'09), 北京, 2009-12-12.

[17] Cormack A M, Rusnak J, Baldwin C Y. Exploring the structure of complex software design:An empirical study of open source and proprietary Code[J].Management Science,2006,52(7):1015-1030.

[18] Estrin G, Bussell B,Turn R,et al. Parallel processing in a restructurable computer system[J]. IEEE Trans ations on Electronic Computers,1963,12(6):747-755.

[19] 田军,李莉芳,白剑,等. 基于DSM的应急任务流程模块化设计研究[J],中国管理科学,2014,22(8):100-107.

[20] Liang Yan, Bao Jinsong, Hu Xiaofeng, et al. A heuristic project scheduling approach for quick response to maritime disaster rescue[J]. International Journal of Project Management,2009,27(6):620-628.

[21] Sprecher A, Hartmann S, Drexl A. An exact algorithm for project scheduling with multiple modes[J]. OR Spektrum,1997,19(3):195-203.

[22] Akkan C, Drexl A, Kimms A. Network decomposition-based benchmark results for the discrete time-cost trade-off problem[J]. European Journal of Operational Research,2005,165(2):339-358.

[23] De Reyck B, Demeulemeester E, Herroelen W. Local search methods for the discrete time/resource trade-off problem in project networks[J]. Naval Research Logistic Quarterly,1998,45(6):553-578.

[24] Salewski F, Schirmer A,Drexl A. Project scheduling under resource and mode identity constraints:Model, complexity, methods, and application[J]. European Journal of Operational Research, 102(1):88-110.

[25] Kolisch R, Hartmann S.Heuristic algorithms for the resource-constrained project scheduling problem:Classification and computational analysis[M]//Weglarz J.Project scheduling:Recent models, algorithms, and applications. Boston,Kluwer Academic Publishers,1999:147-178.
Outlines

/